Construction Management
 

The Birches Pump Station and Force Main, Locust Valley, NY

County of Nassau
Construction for this $8 million project included a sewage pump station and 3 miles of sewer force main to connect an isolated subdivision to the Nassau County Sewer System.  Services by de Bruin included scheduling, resident engineering, inspection, administration of contract payments, administration of submittals and RFI's, review and negotiation of change orders, monitoring and reporting on progress, running project meetings, shop witness testing, oversight of start-up, testing and training, and contract close-out.

 

Cedar Creek WPCF Final Tank & Building Improvement, Wantagh, NY

County of Nassau
de Bruin provided construction management and inspection for the demolition of eight final tanks and two buildings and construction of six concrete final tanks and a new process building with associated pumps and equipment, a computer center capable of controlling a large portion of the plant, an extensive HVAC/mechanical room and motor control center/electrical room and storage area for spare parts.  The overall construction cost was $27,500,000. 

 

Cedar Creek WPCF Sludge Dewatering Facility Improvement, Wantagh, NY

County of Nassau
The existing facility was an operation that contained antiquated equipment that was beyond repair.  The project included a 8,300 square foot extension of the existing building and demolition of the existing building interior including all S Building equipment, controls, mechanical, architectural, and all ancillary equipment.  Construction included installation of ten new belt presses, a new instrumentation/control system, all new pumps, tanks, odor control system, security system, truck loading area with conveyors and pricing.  Construction cost was $32,000,000. Our responsibilities included project engineering, construction inspection, conducting foreman's and project meetings, negotiation of change orders, project estimate, contractor claims evaluation, preliminary review of RFI's, shop witness testing, blue tag/yellow tag and system startup and scheduling.

 

Bay Park STP Hot & Chilled Water Piping Replacement, East Rockaway, NY

County of Nassau
de Bruin provided construction inspection and scheduling for the replacement of deteriorated and leaking piping of the hot and chilled water distribution piping system with a new fiberglass insulated piping system that enters and exits cast in place structures throughout the facility.  Critical to the project was maintaining continuous operation with a temporary feeder system and by pass piping to the existing buildings.  The overall construction cost was $6,500,000.

 

Whitewood Drive Pumping Station, Massapequa, NY

County of Nassau
This multi prime project included the demolition and removal of all components, including mechanical, electrical, heating, ventilation, plumbing, piping, conduit and all pump station equipment including the emergency generator and existing pumps and controls.  Installation of bypass pumping facility and appurtenances preceded the demolition of the facilities.  Construction of a new masonary structures included wood frame, roof, doors and ceiling over the existing pump station substructure, furnished and installed new pumps and controls, piping, valves, pump control equipment, electrical and heating and ventilation.  Dewatering system was installed during construction.  The construction cost was $2,181,410.  Our responsibilities included project engineering, review of all shop drawings, O&M manuals, startup procedures and asbuilts, RFI responses, negotiation of change orders, contractor claim evaluation, project inspection and surveying.

 

Cedar Creek WPCF Aeration Tank Covers & Odor Control Building, Wantagh, NY, Town of Oyster Bay
This project was initiated to reduce odors at the facility and the surrounding community.  The scope of the project involved covering the aeration tanks with an aluminum extruded cover system and constructing an odor control building that would remove odors from the aeration tank by scrubbing the air stream. The project was both equipment and labor intensive.  Extensive testing was conducted on both the cover and the odor control system.  Testing was conducted 24 hours/day over an extended period of time, which included both recording data and inspection.  Once the testing was approved, the entire system was balanced and placed into operation. The construction cost was $15,000,000.  Our responsibilities included project engineering, construction inspection, RFI responses, negotiation of change orders, contractor claims evaluation, and scheduling. 

 

Cedar Creek WPCF Digester Rehabilitation, Wantagh, NY

County of Nassau
The Cedar Creek Digester Control building was a facility that needed to be upgraded in order to meet local codes and ordinances for a gas gas containing structure.  Construction included structural concrete work, new petitions with structural glazed tile, upgrade of electrical and HVAC systems, installation of new equipment and fire protection system.  Project scheduling was critical as numerous shut downs were necessary to accomplish the work.  This required extensive coordination with plant personnel, contractors and the construction management team.  The construction cost was $6,000,000.  Our responsibilities included project engineering, construction inspection, RFI responses, negotiation of change orders, contractor claims evaluation, and scheduling.

 

Clark Street Park, Long Beach, NY

City of Long Beach
de Bruin provided design and construction management/inspection services for the renovation of an one acre waterfront park.  Work included demolition of existing hardscape and construction of meadows, natural paths, benches, decorative railings on the bulkhead, a comfort station, utilities, and a sprayground.  The construction cost was $650,000.  Our responsibilities included design, resident engineering, inspection, administration of contractor payments, administration of submittals and RFI's, review and negotiation of change orders, monitoring and reporting on progress, running project meetings, and contract close-out.

 
Tappen Beach Launching Ramps, Sea Cliff, NY

Town of Oyster Bay
The objective of the project was to replace an existing boat ramp that had been closed due to deterioration with two new concrete boat ramps 112' in length incorporated with a 300' PVC bulkhead reinforced with a helical pile tie back system.  Construction included demolition of the existing boat ramp, a cofferdam and dewatering system, 7,500 cubic yards of dredging, floating dock, timber cap and rail, and parking field.  The construction cost was $1,200,000.  Our services included project management, survey, site and utility design, DEC permitting for construction in environmentally sensitive areas, New York State Department of Parks Grant Administration, and construction management.

   
11 Union Avenue   Bethpage   New York   11714-5811   T: 516.513.1313   F: 516.579.2574
Website Builder