Garden City Community Park Pool Redevelopment, Garden City, NY

Village of Garden City

Implemented a phased program to renovate the outdoor pool complex consisting of a recreational pool, wading pool, and a competitive swimming pool.

Phase 1, 2002

Complete renovation of recreational pool with replacement of filter systems, replacement of diving boards with two 150’ long water slides, construct of rimflow gutter with perimeter surge trench, and construct a new 2,500 square foot wading pool.  Replace pool decks and add sunshelters.

Phase 2, 2002

Renovated the competitive swimming pool with the replacement of filter systems, installation of a handicap access ramp into the pool, installation of stainless steel overflow channel, and installation of PVC liner in pool.  Estimated cost for Phase 1 and 2: $2,800,000

Pool Redevelopment, 2012

Existing wading pool was removed and a new wading pool with interactive water features constructed.  A greenhouse was demolished to make way for the new filter building and equipment that serves the wading pool and a new drywell installed for backwash. The decks around the wading pool were redesigned to make better use of the space and additional playground equipment installed.  Partial renovation of the recreational pool included replacement of the rimflow coping stones and rehabilitation of the pool slide.  Site work included the removal of trees and a raised deck near the competitive swimming pool for more deck space, relocated a maintenance road, installed new walkways, restored lawn areas, installed fencing and sun shelters.  Estimated cost: $1,775,000.

 

Siwanoy Country Club Pools, Bronxville, NY

Siwanoy Country Club
The complete renovation project included reconfiguring the 3,500 square foot swimming pool's outline, modifying the swim lanes to be code compliant to race course standards, modifying the diving hopper to be code compliant with Department of Health regulations for a 1 meter board and modifying the shallow end of the pool to provide improved recreational swim area.  The existing wading pool was replaced with a new pool triple the size and with a zero depth entry.  All pool deck equipment was replaced, as well as the pool recirculation, filtration, and treatment equipment.  The pool deck and deck drainage system was also replaced.

 

Bay Terrace Country Club Pools, Bayside, NY

Bay Terrace Country Club 
The 6,000 square foot swimming pool had a wading pool area within the pool, the pool was leaking and the pool deck was in a deteriorated condition. The project objective was to renovate the pool and add a separate wading pool with interactive water features.  The swimming pool, now one of the largest in Queens, has depths ranging from 3 feet to 8 feet and includes an ADA accessible ramp, lap lanes, two slides and plenty of open swim areas.  All pool deck equipment was replaced, as well as the pool recirculation, filtration, and treatment equipment.  The pool deck and deck drainage system was also replaced. 

 

SUNY Old Westbury Natatorium, Old Westbury, NY

SUNY Old Westbury
The project objective was to correct significant water loss problems occurring in the 45' x 75' indoor swimming and diving pool and upgrading the pool recirculation, filtration, and treatment equipment that was over 20 years old.  Additional work included rehabilitating the pool finish, natatorium deck and drainage system. 

 

Bethpage High School Pool, Bethpage, NY

Bethpage School District
The project consisted of renovating the existing 25 meter pool for high school competition.  Work included new gutter system, repairs to leaking issues, and new deck equipment.
 

Engineers Country Club Pool, Roslyn Harbour, NY

Engineers Country Club
Renovation of swimming pool and gutter system including replacement of pool recirculation, filtration, and treatment equipment, modify surge tank, installation of double slide, replacement of pool deck and surrounding patio.

 

Bethpage Park Pool Filter Building, Bethpage, NY

Town of Oyster Bay
Designed the renovation of the filter building and conversion of the pool from D.E. filters to high-rate sand filters.  Design included replacement of the pool recirculation system, pool control equipment and an enclosed vault for chlorine storage tanks. 

 

Nickerson Beach Park Pool Filters, Lido, NY

County of Nassau

The $120,000 pool filtration systems upgrade was for the east and west pavilion pools located on either end of the park on the Atlantic Ocean. The upgrade included replacing the existing pool filtration systems with new high rate sand filters to improve operation and bring the facility into compliance with health codes. Our services included survey, cost estimates, specifications, construction documents, permitting, construction management and inspection.

 

Westchester Hills Condominium Pools, Elmsford, NY

Westchester Hills Condominium
Design for the $400,000 reconstruction of a swimming pool and wading pool and replacement of pool recirculation, filtration, and treatment equipment, replacement of the pool deck, fence, drainage, and new ADA ramp.  Our services included survey, cost estimates, specifications, construction documents, permitting, construction management and inspection. 

   